Song Da 11 Joint Stock Company attended the launching ceremony of the emulation and association to build synchronous power grid projects of Van Phong 1 BOT thermal power plant
Attending the ceremony were Mr. Duong Quang Thanh – Chairman of EVN’s Member Council, Mr. Do Duc Hung – Chairman of Vietnam Electricity Trade Union. On the side of the National Power Transmission Corporation (EVNNPT), there were Mr. Nguyen Tuan Tung – Chairman of the Board of Members of the National Power Transmission Corporation (EVNNPT), Mr. Pham Le Phu – General Director of EVNNPT, Mr. Nguyen Ngoc Tan – Thanh Member of the Board of Directors of EVNNPT, Mr. Bui Van Kien – Deputy General Director of EVNNPT, Mr. Vu Tran Nguyen – Deputy General Director of EVNNPT, Mr. Trinh Tuan Son – Chairman of EVNNPT’s Trade Union, Mr. Nguyen Duc Tuyen – Director of Project Management Board of Power Projects Central Region (CPMB), Mr. Nguyen Cong Thang – Director of Power Transmission Company 3. Attending the ceremony were leaders of contractors involved in the construction of the project.
The importance of the project
Over the years, following the direction of the Prime Minister and the Ministry of Industry and Trade, Vietnam Electricity has completed the negotiation and signed the Power Purchase Agreement for the Van Phong 1 BOT Thermal Power Plant Project, and at the same time assigned to The National Power Transmission Corporation focuses on investing in synchronously connected power grid projects. These are key projects to ensure power supply for the South Central and Southern regions from 2023 onwards.
According to the provisions of the power purchase and sale contract and the BOT contract of the Van Phong 1 BOT thermal power plant project, EVN is obliged to complete the 500kV Van Phong – Vinh Tan transmission line project no later than December 26, 2022. If the project is completed later than this milestone, EVN will have to pay huge expenses every day. At the same time, after 6 months, if it cannot be overcome, the investor has the right to terminate the project and the Ministry of Industry and Trade must buy back the project according to the provisions of the BOT contract. If this happens, it will cause loss, economic damage and affect the reputation of the Government of Vietnam, the Ministry of Industry and Trade, as well as the Electricity of Vietnam with investors.
In addition to releasing the capacity of Van Phong 1 BOT Thermal Power Plant, the investment in construction of synchronous power grid projects to release the capacity of Van Phong 1 BOT Thermal Power Plant is also very important in the operation of the transmission grid. ensure electricity supply and make a significant contribution to the socio-economic development, security and defense for the provinces in the South Central Coast region; clearing capacity of power plants using renewable energy in Khanh Hoa, Ninh Thuan and neighboring provinces; contributing to ensuring electricity supply for the South, creating a strong link between the central and southern power systems, as well as having an important meaning in the economic operation of the national power system.
Concentrating resources to ensure project progress
Speaking at the launching ceremony of joint emulation, Chairman of EVN Member Council Duong Quang Thanh assigned tasks to National Power Transmission Corporation, Central Power Project Management Board, contractors, consulting units and relevant units, must appoint responsible leaders to follow the line to focus on organizing and operating the construction site, mobilizing all resources and better coordinate with localities in accelerating and accelerating progress. The site clearance level as well as the project’s construction schedule, ensure completion on schedule as committed no later than December 26, 2022.
Requesting the units to continue to promote the experience and results achieved through the emulation movements on the transmission grid projects in the past years to continue emulating production labor on the construction works. synchronous power grid project to release capacity of Van Phong 1 BOT Thermal Power Plant, complete energizing on time and ahead of schedule, ensuring quality, efficiency and meeting technical requirements.
Mr. Nguyen Tuan Tung – Chairman of the Board of Members of EVNNPT said: Aware of the importance and urgency of the projects, EVNNPT’s leaders have directed the specialized departments of the Corporation and CPMB to focus on human resources and implementation. synchronous solutions to ensure the progress of completing projects.
Currently, EVNNPT/CPMB regularly works with localities, contractors and related units to promptly solve difficulties and problems arising on the construction site. Regularly update the implementation situation, difficulties and problems in the land clearance work to promptly report to the National Steering Committee for Power Development, EVN.
At the ceremony, Mr. Do Duc Hung – Chairman of the Vietnam Electricity Trade Union launched the Joint Directive of the General Director of EVN and the Standing Board of the Vietnam Electricity Trade Union on emulation and cooperation to complete the progress of the projects. judgment.
Link Competition Content:
1. Emulation objective: Create an exciting emulation atmosphere so that the units participating in the construction, unite and work together to strive to complete the project.
2. Emulation period: From March 18 to December 25, 2022.
3. Subjects participating in the emulation: Collectives and individuals participating in the construction of clusters of works to release capacity of Van Phong Thermal Power Plant.
4. Specific objectives:
– Project of 500kV transmission line Van Phong thermal power plant – Vinh Tan power plant
+ Completed foundation casting: June 30, 2022
+ Completed the erection of columns: August 31, 2022
+ Finish pulling the rope: November 30, 2022
+ Completion of acceptance test and energizing: December 25, 2022
– Van Phong 500kV substation project and connection; Project of 500kV transmission line connecting Thuan Nam 500kV substation to 500kV Van Phong – Vinh Tan transmission line: Completed the acceptance test and energised on December 25, 2022.
Implementation commitment of Song Da Joint Stock Company 11.
Song Da 11 Joint Stock Company as a construction and installation contractor for package 5, the 500kV Van Phong – Vinh Tan transmission line. Realizing the importance of the Project, after signing a contract with the Investor. The company has mobilized human resources, machinery and equipment to the construction site, ensuring the progress targets set by the Investor. The Board of Directors of the Company is always interested in closely directing, proactively removing obstacles at the construction site to complete the project as promised.